Study cases · Singapore · Combined solutions

Chiller and DX energy savings in Singapore: what Radiant+ E3, MaxR100 and Aquene save together

Six study cases — two water-cooled chillers, two air-cooled chillers and two DX units — priced at Singapore's electricity tariff and grid emission factor, running 300 days a year. They show the money saved each year, how fast the treatment pays for itself and how much CO₂ it avoids.

  • S$0.30 per kWh Singapore tariff
  • 0.402 kg CO₂ per kWh (EMA grid emission factor)
  • 300 days × 24 hours a year
S$196,963Saved a year, 1,000 RT water-cooled chiller at 15%
2.2 yrSimple payback
264 tCO₂ avoided a year

How much can combined Radiant+ E3, MaxR100 and Aquene treatment save a Singapore chiller plant?

At Singapore's electricity tariff (S$0.30/kWh), grid emission factor (0.402 kg CO₂/kWh) and 300 days of 24-hour operation, a 15% saving on a 500–1,000 RT water-cooled chiller is worth S$98,000–S$197,000 a year, pays back in about 2.2 years and avoids 132–264 tonnes of CO₂ a year. Air-cooled chillers of 500–1,000 kW save S$39,000–S$78,000 a year with payback under 3 years, and a single 12–16 HP DX unit saves about S$3,500–S$4,600 a year with payback of about 2.4 years.

CaseSolutionsTreatment costSaved / year at 15%Payback at 15%CO₂ avoided / year at 15%
500 RT water-cooled chillerMaxR100 + AqueneS$216,500S$98,4822.2 yr132 t
1,000 RT water-cooled chillerMaxR100 + AqueneS$427,500S$196,9632.2 yr264 t
500 kW air-cooled chillerRadiant+ E3 coil coating + MaxR100 + AqueneS$113,000S$39,1562.9 yr52 t
1,000 kW air-cooled chillerRadiant+ E3 coil coating + MaxR100 + AqueneS$220,500S$78,3132.8 yr105 t
12 HP DX unitRadiant+ E3 coil coating + MaxR100S$8,400S$3,4572.4 yr5 t
16 HP DX unitRadiant+ E3 coil coating + MaxR100S$10,900S$4,5622.4 yr6 t
Simple payback by case at 10%, 15% and 20% energy savingsHorizontal bars: water-cooled cases pay back in 1.6 to 3.3 years, air-cooled cases in 2.1 to 4.3 years, DX units in 1.8 to 3.6 years, at Singapore tariff of S$0.30 per kWh and 7,200 operating hours a year.0 yr1 yr2 yr3 yr4 yr5 yr10% saving15% saving20% saving500 RT water-cooled chiller3.3 yr2.2 yr1.6 yr1,000 RT water-cooled chiller3.3 yr2.2 yr1.6 yr500 kW air-cooled chiller4.3 yr2.9 yr2.2 yr1,000 kW air-cooled chiller4.2 yr2.8 yr2.1 yr12 HP DX unit3.6 yr2.4 yr1.8 yr16 HP DX unit3.6 yr2.4 yr1.8 yr
Simple payback for each case at 10%, 15% and 20% energy saving. Singapore tariff S$0.30/kWh, 7,200 operating hours a year.

What assumptions are these figures based on?

Every figure on this page uses the same three Singapore inputs, so you can check any number with a calculator.

Electricity tariff
S$0.30 per kWh — in line with the SP Group regulated tariff for Q4 2026 (28.59 ¢/kWh before GST, 31.16 ¢/kWh with GST). Commercial contract rates vary
Carbon emission factor
0.402 kg CO₂ per kWh — Singapore's average grid emission factor for 2024, published by the Energy Market Authority (EMA)
Operating hours
300 days a year × 24 hours = 7,200 hours
Money saved
Baseline kWh × saving % × S$0.30
CO₂ avoided
kWh saved × 0.402 kg
Simple payback
Treatment cost ÷ money saved per year
Net after 5 years
5 × money saved per year − treatment cost; no tariff escalation, discounting or re-treatment

These are projections for typical plants, not measured results from a single site. The saving percentages are scenarios chosen from the range measured in RCT's field projects (see the evidence below). We confirm your own baseline and saving by measuring before and after.

Why combine Radiant+ E3, MaxR100 and Aquene on one system?

Each technology removes a different loss, so their effects add up: Radiant+ E3 restores the air-cooled condenser coil, MaxR100 cleans oil fouling inside the refrigerant circuit, and Aquene improves heat transfer in the chilled-water loop.

Chiller plant diagram showing oil fouling in refrigerant pipes, plain chilled water and oxidised condenser coils
Three loss points in a chiller plant: (1) oil fouling — MaxR100; (2) plain chilled water — Aquene; (3) oxidised air-cooled condenser coils — Radiant+ E3.
  • Radiant+ E3 coil coating — air-cooled chillers only. Restores and protects the condenser coil so heat is rejected at lower head pressure. How Radiant+ E3 works
  • MaxR100 — all chillers. Releases oil films from evaporator and condenser tube walls inside the refrigerant circuit and reduces compressor friction. How MaxR100 works
  • Aquene — all chillers. Graphene heat transfer fluid in the closed chilled-water loop, improving evaporator heat exchange. How Aquene works

Water-cooled chillers have no air-side coil, so they are treated with MaxR100 and Aquene only. DX and VRF units have no chilled-water loop, so they are treated with Radiant+ E3 and MaxR100.

500 RT water-cooled chiller: savings, payback and CO₂

At a 15% saving, the 500 RT water-cooled chiller saves about S$98,482 and 132 tonnes of CO₂ a year, and the S$216,500 treatment pays back in 2.2 years.

S$98,482Saved per year at 15%
2.2 yrSimple payback at 15%
132 t CO₂Avoided per year at 15%
S$275,908Net saving after 5 years at 15%
Equipment
Water-cooled centrifugal chiller, 500 RT (≈1,758 kW cooling)
Solutions combined
MaxR100 + Aquene
Baseline consumption
2,188,479 kWh a year (≈304 kW average, ≈0.61 kW/RT) — S$656,544 and 880 t CO₂ a year
Treatment cost (contract price)
S$216,500
Energy savingkWh saved / yearMoney saved / yearCO₂ avoided / yearSimple paybackNet after 5 years
10%218,848 kWhS$65,65488.0 t3.3 yrS$111,772
15%328,272 kWhS$98,482132.0 t2.2 yrS$275,908
20%437,696 kWhS$131,309176.0 t1.6 yrS$440,044

1,000 RT water-cooled chiller: savings, payback and CO₂

At a 15% saving, the 1,000 RT water-cooled chiller saves about S$196,963 and 264 tonnes of CO₂ a year, and the S$427,500 treatment pays back in 2.2 years.

S$196,963Saved per year at 15%
2.2 yrSimple payback at 15%
264 t CO₂Avoided per year at 15%
S$557,316Net saving after 5 years at 15%
Equipment
Water-cooled centrifugal chiller, 1,000 RT (≈3,517 kW cooling)
Solutions combined
MaxR100 + Aquene
Baseline consumption
4,376,958 kWh a year (≈608 kW average, ≈0.61 kW/RT) — S$1,313,087 and 1,760 t CO₂ a year
Treatment cost (contract price)
S$427,500
Energy savingkWh saved / yearMoney saved / yearCO₂ avoided / yearSimple paybackNet after 5 years
10%437,696 kWhS$131,309176.0 t3.3 yrS$229,044
15%656,544 kWhS$196,963263.9 t2.2 yrS$557,316
20%875,392 kWhS$262,617351.9 t1.6 yrS$885,587

500 kW air-cooled chiller: savings, payback and CO₂

At a 15% saving, the 500 kW air-cooled chiller saves about S$39,156 and 52 tonnes of CO₂ a year, and the S$113,000 treatment pays back in 2.9 years.

S$39,156Saved per year at 15%
2.9 yrSimple payback at 15%
52 t CO₂Avoided per year at 15%
S$82,781Net saving after 5 years at 15%
Equipment
Air-cooled chiller, 500 kW (≈142 RT)
Solutions combined
Radiant+ E3 coil coating + MaxR100 + Aquene
Baseline consumption
870,139 kWh a year (≈121 kW average, ≈0.85 kW/RT) — S$261,042 and 350 t CO₂ a year
Treatment cost (contract price)
S$113,000
Energy savingkWh saved / yearMoney saved / yearCO₂ avoided / yearSimple paybackNet after 5 years
5%43,507 kWhS$13,05217.5 t8.7 yrS$-47,740
10%87,014 kWhS$26,10435.0 t4.3 yrS$17,521
15%130,521 kWhS$39,15652.5 t2.9 yrS$82,781
20%174,028 kWhS$52,20870.0 t2.2 yrS$148,042

1,000 kW air-cooled chiller: savings, payback and CO₂

At a 15% saving, the 1,000 kW air-cooled chiller saves about S$78,313 and 105 tonnes of CO₂ a year, and the S$220,500 treatment pays back in 2.8 years.

S$78,313Saved per year at 15%
2.8 yrSimple payback at 15%
105 t CO₂Avoided per year at 15%
S$171,063Net saving after 5 years at 15%
Equipment
Air-cooled chiller, 1,000 kW (≈284 RT)
Solutions combined
Radiant+ E3 coil coating + MaxR100 + Aquene
Baseline consumption
1,740,279 kWh a year (≈242 kW average, ≈0.85 kW/RT) — S$522,084 and 700 t CO₂ a year
Treatment cost (contract price)
S$220,500
Energy savingkWh saved / yearMoney saved / yearCO₂ avoided / yearSimple paybackNet after 5 years
5%87,014 kWhS$26,10435.0 t8.4 yrS$-89,979
10%174,028 kWhS$52,20870.0 t4.2 yrS$40,542
15%261,042 kWhS$78,313104.9 t2.8 yrS$171,063
20%348,056 kWhS$104,417139.9 t2.1 yrS$301,584

12 HP DX unit: savings, payback and CO₂

At a 15% saving, the 12 HP DX unit saves about S$3,457 and 5 tonnes of CO₂ a year, and the S$8,400 treatment pays back in 2.4 years.

S$3,457Saved per year at 15%
2.4 yrSimple payback at 15%
5 t CO₂Avoided per year at 15%
S$8,885Net saving after 5 years at 15%
Equipment
DX / VRF outdoor unit, 12 HP (≈9.7 RT)
Solutions combined
Radiant+ E3 coil coating + MaxR100
Baseline consumption
76,824 kWh a year (≈11 kW average, ≈1.10 kW/RT) — S$23,047 and 31 t CO₂ a year
Treatment cost (contract price)
S$8,400
Energy savingkWh saved / yearMoney saved / yearCO₂ avoided / yearSimple paybackNet after 5 years
10%7,682 kWhS$2,3053.1 t3.6 yrS$3,124
15%11,524 kWhS$3,4574.6 t2.4 yrS$8,885
20%15,365 kWhS$4,6096.2 t1.8 yrS$14,647

DX baseline: rated electrical input of 1.1 kW per refrigeration ton (≈COP 3.2) running 7,200 hours a year, i.e. 9.7 RT × 1.1 kW × 7,200 h. This replaces the 270,078 kWh a year in the earlier study slide, which was about 3.5 times what a single 12 HP unit can draw.

16 HP DX unit: savings, payback and CO₂

At a 15% saving, the 16 HP DX unit saves about S$4,562 and 6 tonnes of CO₂ a year, and the S$10,900 treatment pays back in 2.4 years.

S$4,562Saved per year at 15%
2.4 yrSimple payback at 15%
6 t CO₂Avoided per year at 15%
S$11,910Net saving after 5 years at 15%
Equipment
DX / VRF outdoor unit, 16 HP (≈12.8 RT)
Solutions combined
Radiant+ E3 coil coating + MaxR100
Baseline consumption
101,376 kWh a year (≈14 kW average, ≈1.10 kW/RT) — S$30,413 and 41 t CO₂ a year
Treatment cost (contract price)
S$10,900
Energy savingkWh saved / yearMoney saved / yearCO₂ avoided / yearSimple paybackNet after 5 years
5%5,069 kWhS$1,5212.0 t7.2 yrS$-3,297
10%10,138 kWhS$3,0414.1 t3.6 yrS$4,306
15%15,206 kWhS$4,5626.1 t2.4 yrS$11,910
20%20,275 kWhS$6,0838.2 t1.8 yrS$19,513

DX baseline: 12.8 RT × 1.1 kW/RT × 7,200 h. This replaces the 350,086 kWh a year in the earlier study slide. Units running below full load use less, so savings and payback scale with actual metered consumption.

What measured results support these saving scenarios?

The 10–20% scenarios sit inside the savings measured for each technology on real equipment.

  • MaxR100 lowered a 1,100-ton centrifugal chiller's kW/TR by 14.1% (COP 4.72 → 5.50). Read the case
  • Aquene recorded 15.0% to 31.3% savings across 13 chilled-water projects, including a shopping mall in Singapore at 15.0%. See the project list
  • Radiant+ E3 cut energy by 12% to 28% on field projects and restored a corroded coil to new-unit efficiency in a CSIRO test. See the results

Ask for a measured trial on your equipment

Frequently asked questions

Are these measured results?

No. They are projections for typical chillers, using measured saving ranges from RCT's field projects and Singapore's tariff, grid emission factor and operating hours. On a real project RCT measures the baseline and the saving before and after treatment.

What if my tariff or operating hours are different?

Money saved scales directly with both. For example, a plant running 12 hours a day, 300 days a year, saves half the amounts shown, and payback doubles. Ask us to rerun the numbers with your bills.

Why is the air-cooled payback longer at the same saving percentage?

An air-cooled chiller of 500–1,000 kW uses less electricity in total than a 500–1,000 RT water-cooled chiller, so the same percentage is fewer kWh, while the treatment also includes coil coating.

Which Singapore emission factor is used?

0.402 kg CO₂ per kWh, the average grid emission factor for 2024 published by the Energy Market Authority.