What must a Singapore building owner do under BCA's Mandatory Energy Improvement and Periodic Energy Audit requirements?

Under the Mandatory Energy Improvement (MEI) regime, owners of energy-intensive buildings of 5,000 m² GFA or more who receive an MEI audit notice must appoint a qualified professional, submit an energy audit and improvement plan, cut energy use intensity by 10% within three years and maintain it for a year. Under Periodic Energy Audit (PEA) rules, owners of buildings covered by BCA's cooling-system requirements must have the chilled-water plant's operating efficiency audited when BCA serves a notice. Audits and submissions must be done by a Professional Engineer (Mechanical) or a BCA-registered Energy Auditor.

Which buildings does the Mandatory Energy Improvement regime cover?

Existing buildings with a gross floor area of 5,000 m² or more, in specified types, that BCA assesses as energy-intensive. The regime took effect on 30 September 2025.

Building types
Commercial (offices, hotels, retail), healthcare facilities, institutional buildings (educational, civic, community, cultural), sports and recreation centres, and mixed developments of these
Size
Gross floor area of 5,000 m² or more
Energy-intensive
The building has exceeded the energy use intensity (EUI) threshold for its sub-typology for three consecutive years before the notice. BCA says thresholds are roughly at the 75th percentile of EUI for that sub-typology, so the regime targets buildings consistently in the top quarter of energy use. Mixed-use buildings use a pro-rated threshold
Trigger
The Commissioner of Building Control issues an MEI audit notice to the owner
Scale
BCA estimated that fewer than 100 buildings would be in the first batch

What must the owner do after receiving an MEI audit notice?

Follow four stages: appoint a qualified professional, submit an audit and improvement plan, implement it, and maintain the improvement.

StageOwner's obligationDeadline
1. AppointEngage a Specified Individual — a Professional Engineer (Mechanical) with a practising certificate, or a BCA-registered Energy Auditor — to audit the building and its systemsWithin 90 days
2. Audit and planSubmit the energy audit report and an Energy Efficiency Improvement Plan (EEIP) to BCAWithin 1 year of the notice
3. ImplementCarry out the measures to reduce EUI by at least 10% from the average EUI of the three years before the noticeWithin 3 years of the EEIP submission
4. MaintainKeep the improved performance for one year, then submit a maintenance reportReport within 3 months after the one-year period

The regime is outcome-based: owners choose their measures, from maintenance and replacing faulty parts and sensors to chiller-plant optimisation or major retrofits. BCA's FAQs put a typical energy audit at no more than S$50,000.

What does the Periodic Energy Audit require?

When BCA serves a PEA notice, the owner must have the building's chilled-water plant audited for operating system efficiency by a PE(Mechanical) or BCA-registered Energy Auditor, and submit the results to BCA.

Buildings covered
Buildings whose planning permission application was submitted on or after 1 December 2010; and existing buildings that underwent a major energy-use change (installing, replacing or substantially altering the cooling system) on or after 2 January 2014. Data centres, religious buildings, residential buildings other than serviced apartments, utility buildings, and industrial, railway, port and airport facilities are exempt
When
Notices are served at intervals of not less than three years; for retrofitted existing buildings the first comes no less than 36 months after as-built approval
What is measured
Operating system efficiency of the chilled-water plant, sampled every minute continuously for at least one week of normal operation; water-cooled plants must show heat balance within ±5% for at least 80% of points
Standard
The minimum efficiency that applied when the plant's design was submitted — for example, about 0.68 kW/RT water side and 0.9 kW/RT total system efficiency for water-cooled plants submitted on or after 1 June 2022
Submission
Through CORENET (Form BCA-EB-OSE01) within the time stated in the notice
If it fails
The owner must carry out maintenance or other measures to bring the system back into compliance

What other BCA obligations apply to existing buildings?

Owners submit building information and energy consumption data to BCA every year, and must make a design submission to BCA before installing or replacing chillers.

The annual submission (via the Building Energy Submission System) is what BCA uses to benchmark buildings and identify those that may be energy-intensive under MEI.

How can RCT help?

The statutory audit, the improvement plan and the submissions must be done by the owner's PE(Mechanical) or BCA-registered Energy Auditor. RCT supports the owner and that professional with measurement, energy-saving measures and verified results.

For buildings facing an MEI target, low-disruption measures such as AI plant optimisation, MaxR100, Aquene and Radiant+ E3 can contribute to the 10% EUI reduction; see Singapore savings estimates.

Official sources: BCA — Mandatory Energy Improvement regime; BCA — MEI FAQs; BCA — Periodic Energy Audits; Code on Periodic Energy Audit of Building Cooling Systems, Edition 4.0; BCA — requirements for existing buildings. Rules and schemes change; check the current version before acting.

Ask RCT to review your plant data All HVAC energy questions

Frequently asked questions

Will I be told if my building is subject to MEI?

Yes. The regime applies when the Commissioner of Building Control issues an MEI audit notice; until then, there is no MEI obligation, although the annual energy data submission still applies.

Can my facilities manager do the audit?

Only if he or she is a Professional Engineer (Mechanical) with a practising certificate or a BCA-registered Energy Auditor.